New development across 3,700 square meters
Preparations for the construction of a new assembly hall started at the beginning of 2017. Many of the old halls were demolished to make room for a new storage facility as well as a modern production hall covering an area of 3,700 square meters. Tobias Oberle (general contractor for the building project, FREYLER), Reinhold Groß (Managing Director of TRUMPF Teningen at the time), Patricia Garcia (architect, FREYLER), Heinz-Rudolf Hagenacker (Mayor of Teningen), Joachim Saar (representative of the Mayor of Emmendingen) and Michael Fischer (plant manager of TRUMPF Teningen) met on 24 March 2017 for the symbolic ground-breaking ceremony.